Searose FPSO
Client: Harland & Wolff
Location: Belfast Docks
Accommodate was contracted to support Harland & Wolff for a major project at Belfast Docks. The initial contract involved providing workforce accommodation and a range of essential services, including catering, transport, and cleaning, for a total of 183 personnel arriving between February 8th and 15th, 2024. This figure quickly grew to 700 personnel with the project finishing in October 2024. Below is a breakdown of what we delivered.
January 31st, 2024: Accommodate secured additional contracts to manage hospitality, transport, and laundry services for the project.
Infrastructure setup: Accommodate installed kitchens and canteens on-site, capable of serving up to 1,000 personnel, and also established an on-site convenience store to meet the day-to-day needs of the workforce.
February 8th, 2024: The first wave of personnel arrived on-site.
Peak of the project: Over 700 personnel were housed, spread across six different contractors.
Accommodation & Housekeeping:
23,000 rooms cleaned over the course of the project.
Catering:
Transport:
Laundry:
Additional Services:
Corporate hospitality services were provided to support business events and VIP visits.
Accommodate’s comprehensive services ensured smooth day-to-day operations at the Belfast Docks, making it possible for Harland & Wolff to focus on their core business objectives without disruption.